Timeline - Winter Quarter 2015

DATE 
ACTION

January 5, 2015

First Day of Winter Quarter

January 12, 2015

aSAP Forms and Instructions made available

January 20-23, 2015

aSAP Training Offered

January 20, 2015

9:00-10:00am, Rm 1101

January 21, 2015

12:00-1:00pm, Rm 2346

January 22, 2015

3:00-4:00pm, Rm 1402

January 23, 2015

2:00-3:00pm, Rm 1402

February 13, 2015

Completed aSAPs Due

Completed aSAPs submitted

February 18, 2015

aSAPs Distributed to Sub-committees for Review

March 3, 2015

Sub-committees send out requests for additional information (if needed)

March 10, 2015

Responses to Requests for Additional Information Due

March 11-20, 2015

Sub-committees score aSAPs

Rating summary and comments

March 23-27, 2015

Quarter Break

March 31, 2015

Committee Scoring Submitted to ELT

Summer 2015

Final Decisions and Rationale